Multisector economic conglomerate, pioneering stability
Factory

DAK PSI 3 HYDROPOWER PLANT

Home / Đăkpsi 3 – Hydropower Plant

Overview

The Dak Psi 3 hydropower plant is designed and built on the Dak Psi stream, which is a grade I tributary of the Krong Poko river in the territory of Dak Pxi commune, Dak Ha district, and Tu Mo Rong commune, Tu Mo Rong district, Kon Tum province which is the DakPsi stream’s third hydroelectric step.

Dak Psi 3 Hydropower Plant started construction in December 2010 and was put into operation at the end of August 2012. It is linked to the National Power System via a 22 kV dual highway line from Dak Psi 3 to Dak Psi 3 Plant to Transformer 110/22/11 kV Substation, DakPsi Hydropower Plant 4.

The installed capacity of Dak Psi 3 is Nlm = 15.0 MW (03 units of 3×5 MW). Average annual electricity, Dak Psi 3 plant E0 = 59.92 million kwh

4183 ha

Land area

15 MW

Total capacity

5992 million kWh

Average annual production

The history and development

Dak Psi 3 Hydropower Plant was built in December 2010, completed, and put into commercial operation at the end of August 2012. It is linked to the National Power System via a 22 kV dual highway line from Dak Psi 3 Plant to 110/22/11 kV Transformer Substation of DakPsi Hydropower Plant 3.

Before the industrialization and modernization of the country, it is required to develop the energy industry as a foundation for other industries to develop, leading to an increase in energy demand. In particular, the investment in the construction of hydroelectric plants will significantly supplement the energy source for the national power system and get a part of the electricity demand in the region, reducing the power shortage situation in the system, especially during peak hours. At the same time, when the plant is officially put into operation, it will have a positive impact on the local community, create jobs, and improve living conditions for people in the area.